Turret Replacement Downtime

How Much Downtime Does anAmada Turret Replacement Require?

About these figures. The lead time and installation days shown for an Amada turret replacement are TSI estimates, based on what our customers report after dealing with OEM service. Amada does not publish lead times. The TSI schedule figures are our own and you can hold us to them. Have real numbers from an Amada job? Send them to mike@turretsleeving.com and we will correct this page.

Budget 12–16 weeks of lead time for a replacement turret to arrive, then 4–5 days with the machine down for teardown, rigging and OEM installation. From decision to first good part is roughly four months.

Turret sleeving takes 2–3 days of downtime, is usually scheduled within 30 days, and is done in place — the machine never ships. Total elapsed time is about four to five weeks.

Timeline

Where the Weeks Actually Go

Downtime is the number that costs you money, but lead time is the number that decides whether you can react at all. They are different, and quotes often mention only one.

Amada turret replacement EstimatedTime
Quote, approval and order placement1–3 weeks
Manufacture and delivery of the turret assembly12–16 weeks
Machine down: teardown, rigging, OEM installation, alignment4–5 days
Total elapsed, decision to first good part~4 months
TSI turret sleeving Real scheduleTime
Free written estimate returnedwithin 12 hours
Work scheduledusually within 30 days
Machine down: inspect, bore, clean, install sleeves, verify2–3 days
Total elapsed, decision to first good part~4–5 weeks
What It Means On The Floor

Four Months of Running on a Worn Turret

The lead time is the part that catches people out. While you wait 12 to 16 weeks for a replacement assembly, the press is still running — on the same worn stations that caused the problem. That means continued misalignment, continued burring, continued tool sharpening and continued scrap, for a third of a year.

Sleeving compresses the whole thing into roughly four to five weeks from decision to finished, with only 2 to 3 days of that spent with the machine down. Most of our customers schedule it over a planned shutdown or a long weekend and never lose a production day.

There is also no shipping either way. Our field engineers bring the boring equipment to your facility, so the machine stays exactly where it is.

Find Out What Your Machine Actually Needs

A free wear inspection tells you which stations are out of tolerance and what it would cost to put them right. No obligation, written estimate back within 12 hours.